Work Begins On Perrine Coulee Bridge
Twin Falls, Idaho (KMVT-TV) Crews will begin to apply an epoxy overlay to the Perrine Coulee Bridge on U.S. 93, Pole Line Road this week.
Traffic will be reduced to one lane in each direction between Canyon Crest Drive and Harrison Street for about three days. Before applying the epoxy resin and gravel aggregate, crews will clean the surface of the roadway and sidewalk. About half of the bridge will be closed at the time. Kimberly–based Idaho Construction Company is the contractor for the $565,000 project. Comments ( |
Most Viewed
|